Lien waiver

Also called: Lien release, Waiver of lien, Conditional lien waiver

A lien waiver is a document in which a contractor, subcontractor or supplier gives up some or all of its right to file a lien on a property, usually in exchange for payment.

Lien waivers usually come in four types. A conditional waiver takes effect only once payment actually clears. An unconditional waiver takes effect immediately, whether or not payment has arrived. Each can be for a progress payment (covering work through a date) or a final payment (covering the whole job).

Some states require specific statutory waiver forms, and the deadlines and notices needed to preserve lien rights vary widely.

Example

For example, a general contractor asks an electrical supplier for a lien waiver before releasing payment for materials delivered through March 31. The supplier signs a conditional progress waiver, so its rights for that amount are waived only once the payment clears.

Why it matters for getting paid

A common practice is to provide conditional waivers when you request payment and unconditional waivers only after the payment has actually cleared. Keep copies of every waiver you sign and receive, organized by job, since you may need them at closeout.

Lien rights are one of the strongest tools contractors and suppliers have for getting paid on construction jobs, and waiving them too early can remove that protection. Signing the right type of waiver at the right time matters.